1.2. VALUATION METHOD ( kaedah penilaian unit )

Advantages 

  1. Simple technique to calculate the estimate
  2. Fast to get the estimate
  3. Without plan – set estimate
  4. Can imagine the estimate base on : facilities, total of student or patient.
  5. Suitable for construction  WHICH HAS A COMMON UNIT  – need seat, bed :

school, meeting room, hospital, cinemas

Disadvantages

  1. Not accurate
  2. Cannot imagine the design, size, area, height, shape, etc.

Tutorial 1

Base on information below, calculate the construction cost for extra ward to support 300 patient in Dungun Hospital.

HOPITALNO. OF BEDCOST ( RM )
Ulu Terengganu5002,000,000.00
Kemaman10004,500,000.00
Kuala Terengganu10003,000,000.00

Table 1: information of hospital’s bed

Ulu Terengganu          /bed

Kemaman                    /bed

Kuala Terengganu       /bed

 x 300 patient  ( 1 bed = 1 patient)

 x 300            = 3833.33 x 300         = RM1,150,000